Hi Mr. Anil Kumar
Can you try the following Solution
Error executing J expression : 'ACE2_rc ACE2_xids ACE2_Package' =: Pack 90 error running GTP
(1)
Technote (troubleshooting)
Problem(Abstract)
When GTPing, the test reconcile step fails with a pop-up dialog box containing the message below
Symptom
Dialog Box:
The Go To Production process failed.
Unable to reconcile 'elist'
Exception encountered when working with model.
Error executing J expression : 'ACE2_rc ACE2_xids BlockPackages' =: 90 ReconcileBlocks_IModelEdit_NodeGuids;OldBlockPackages;<PackageFormat
PlanningErrorLog:
Error executing J expression : 'ACE2_rc ACE2_xids ACE2_Package' =: Pack 90
Cause
Contributor cannot compare the development and production versions
Resolving the problem
Reset the production version to development
Steps:
In the admin console, reset the production to development (button on the top of the console)
Create, save and remove an access table (in order to force a reconcile job)
Run GTP again
Another Solution which i found on IBM Site is
During GTP: Error executing J expression : 'ACE2_rc ACE2_xids ACE2_Package' =: Pack 90
Technote (troubleshooting)
Problem(Abstract)
When GTPing, the test reconcile step fails with a pop-up dialog box containing the message below
Symptom
Dialog Box:
The Go To Production process failed.
Unable to reconcile '416_acd_skn'
Exception encountered when working with model.
Error executing J expression : 'ACE2_rc ACE2_xids BlockPackages' =: 90 ReconcileBlocks_IModelEdit_NodeGuids;OldBlockPackages;<PackageFormat
PlanningErrorLog:
Error executing J expression : 'ACE2_rc ACE2_xids ACE2_Package' =: Pack 90
Cause
Largest cube too large
Resolving the problem
Split the largest cube into 2