Title: Scheduling Challenge
Post by: rjhare on 23 Jul 2009 05:41:29 AM
My CFO is wanting to change his report schedule (and as he pays me sometimes, I guess I should!)

I need to schedule the reports for the first 10 days of the month....I know it sounds simple, but I haven't a clue after sitting ehre for nearly two hours trying to work it out!

Any help greatly appreciated!

Thanks

Richie
(Cognos 8.4 - Administrator Licence)
Title: Re: Scheduling Challenge
Post by: DustPanMan on 27 Jul 2009 01:54:56 PM
Richie,

Even though it sounds simple, it really is not.  You'll have to create 10 different jobs (1 for each of the first 10 days of the month).  Sorry there isn't an easier way to accomplish this otherwise simple task.

Best regards,

Dustin